Engineering Procurement and Construction Management Contract
Engineering Procurement and Construction Management contracts (EPCM contracts), like Engineering Procurement and Construction contracts (EPC contracts) are similar to design and build contracts, in that there is a single point of responsibility for the design and construction of the project, but generally, the client has less say over the design of the project than on a design and build project, and the contractor takes more risk.
However, unlike an EPC contract, on an EPCM contract the client employs the necessary trade contractors to construct the works. The 'contractor' designs the project, and then acts as a construction manager, co-ordinating the procurement process and then managing the trade contractors. Effectively they are performing the roll of a consultant during the construction phase.
This might be appropriate where the client wishes to retain a degree of control over the procurement process, for example if there is uncertainty about the exact scope or nature of the works required when the procurement process begins. This can be used to accelerate construction by enabling some parts of the works to begin (for example piling) whilst the design of other parts of the works continues.
As the client contracts the trade contractors themselves, they require greater expertise than they would on an EPC contract.
Generally, EPCM contracts are used on engineering and infrastructure projects, where the aesthetics of design might be considered less important to the client than performance and cost certainty.
[edit] Related articles on Designing Buildings
- Contract.
- Contract conditions.
- Construction management.
- EPC contract.
- Procurement route.
- What is an EPC contract?
[edit] External references
- Project Procurement Management Processes
- Skills Funding Agency: Procurement routes.
- CABE: Procurement routes.
- PACE Guidance on the Appointment of Contractors and Consultants for a detailed analysis of the pros and cons of various procurement routes.
- nbs: National Construction Contracts and Law Survey 2012.
- JCT: Deciding on the appropriate JCT contract.
Featured articles and news
Wellbeing in Buildings TG 10/2025
BSRIA topic guide updates.
With brief background and WELL v2™.
From studies, to books to a new project, with founder Emma Walshaw.
Types of drawings for building design
Still one of the most popular articles the A-Z of drawings.
Who, or What Does the Building Safety Act Apply To?
From compliance to competence in brief.
The remarkable story of a Highland architect.
Commissioning Responsibilities Framework BG 88/2025
BSRIA guidance on establishing clear roles and responsibilities for commissioning tasks.
An architectural movement to love or hate.
Don’t take British stone for granted
It won’t survive on supplying the heritage sector alone.
The Constructing Excellence Value Toolkit
Driving value-based decision making in construction.
Meet CIOB event in Northern Ireland
Inspiring the next generation of construction talent.
Reasons for using MVHR systems
6 reasons for a whole-house approach to ventilation.
Supplementary Planning Documents, a reminder
As used by the City of London to introduce a Retrofit first policy.
The what, how, why and when of deposit return schemes
Circular economy steps for plastic bottles and cans in England and Northern Ireland draws.
Join forces and share Building Safety knowledge in 2025
Why and how to contribute to the Building Safety Wiki.
Reporting on Payment Practices and Performance Regs
Approved amendment coming into effect 1 March 2025.